Three Year Paving Plan (2021-2023)
Proposed three-year paving program
This program utilizes funds from the 3 year, $1 million bond approved at 2021 Town Meeting. This program will change based on Town needs, available funds, timing and contractor availability.
Road | Description | Length (ft) | Tonage | Est Cost | Act Cost* | Scheduled |
Brighton Hill Road** |
From Auburn town line to Hebron town line. Culvert replacement, grinding/reclaim as needed, |
21,120 | 5,359.2 | $428,736 | 2021 | |
Death Valley | From Intersection of Marston Hill Road to Harris Road. 2" combined total for tack, shim and overlay. |
8,448 | 2,041.6 | $163,328 | $130,352 | 2021 |
Orchard Fire Station Driveway/Parking Lot |
2" of binder course | $35,000 | $8,877 | 2021 | ||
Holbrook Road |
From Old Buckfield Road toward Auburn town line. Culvert replacement, grinding/reclaim as needed, |
9,504 | 2,411.6 | $192,931 | 2022 | |
Hersey Hill School Road*** | From Intersection of Marston Hill Road to Harris Road. 2" combined total for tack, shim and overlay. |
7,392 | 1,786.4 | $142,912 | 2022/23 | |
Pottle Hill Road**** | From Intersection of Goodwin Road to Woodman Hill Road. 2" combined total for tack, shim and overlay. |
10,032 | 2,545.6 | $203,650 | 2023 | |
TOTAL | 56,496 | 14,144.5 | $1,166,556.80 | $139,229 |
*Actual costs do not include material costs for patching, which are also a paving expense.
**Minot has contracted with the Town of Hebron to complete their section of Brighton Hill Road. Actual material costs and tonnage will be reimbursed after completion.
***Hersey Hill School Road was originally scheduled for FY2023, but Town will attempt to work with contractor to complete in FY2022.
****Original budget includes only 1 mile of Pottle Hill Road, but Town will pave as much as funds will allow of the remaining 2 miles.