Three Year Paving Plan (2021-2023)

Proposed three-year paving program

This program utilizes funds from the 3 year, $1 million bond approved at 2021 Town Meeting. This program will change based on Town needs, available funds, timing and contractor availability.

Road Description Length (ft) Tonage Est Cost Act Cost* Scheduled
Brighton Hill Road**

From Auburn town line to Hebron town line. 

Culvert replacement, grinding/reclaim as needed,
2" combined total for tack, shim and overlay.

21,120 5,359.2 $428,736   2021
Death Valley  From Intersection of Marston Hill Road to Harris Road.
2" combined total for tack, shim and overlay. 
 8,448  2,041.6 $163,328  $130,352  2021 
Orchard Fire Station
Driveway/Parking Lot 
2" of binder course       $35,000 $8,877  2021 
 Holbrook Road

From Old Buckfield Road toward Auburn town line. 

Culvert replacement, grinding/reclaim as needed,
2" combined total for tack, shim and overlay. 

 9,504 2,411.6   $192,931    2022
Hersey Hill School Road***  From Intersection of Marston Hill Road to Harris Road.
2" combined total for tack, shim and overlay.  
7,392  1,786.4   $142,912    2022/23
 Pottle Hill Road**** From Intersection of Goodwin Road to Woodman Hill Road.
2" combined total for tack, shim and overlay.  
 10,032 2,545.6   $203,650    2023
TOTAL     56,496  14,144.5  $1,166,556.80  $139,229  

*Actual costs do not include material costs for patching, which are also a paving expense. 

**Minot has contracted with the Town of Hebron to complete their section of Brighton Hill Road. Actual material costs and tonnage will be reimbursed after completion. 

***Hersey Hill School Road was originally scheduled for FY2023, but Town will attempt to work with contractor to complete in FY2022.

****Original budget includes only 1 mile of Pottle Hill Road, but Town will pave as much as funds will allow of the remaining 2 miles.